
OT begins leachate pilot
study for Red Shield
December 21, 2006
By Greta Sproul
The first three deliveries of leachate from the Juniper Ridge landfill
arrived at the Old Town wastewater treatment plant last Wednesday. The
deliveries were the initial step in an eight-week pilot plan that will
determine whether the plant can continue to treat the leachate for Red
Shield, the new owners of the former Georgia-Pacific mill.
“The
agreement allows them to send three trucks the first week, six trucks
the second week, and six trucks the third week,” Gary Stetson, plant
superintendent said. “We’ll be taking Christmas off, and then we’ll be
accepting six to eight trucks for the last two weeks (of the study).”
As
part of the pilot study, samples of leachate will be taken from two
trucks each week. The trucks will be selected at random and Red Shield
will not be notified before the sampling is done.
Red
Shield is paying for the study, which will follow a civil engineering
proposal from the Topsha-based company, Wright Pierce Engineering. The
cost for the study is not to exceed $38,000.
“Some
of the things we’ll be testing for are soluble BOD, ammonia, sulphate,
sulphite, and arsenic,” Stetson said. “We’re also testing to see if the
leachate is going to cause corrosion in our piping and pumps.”
Stetson says that G-P asked the waste water treatment plant three years
ago to take their leachate, but “we told them that we needed to know
more about it. The idea has been sitting on the backburner (since
then).”
G-P
never followed through on the required testing and continued to take
their leachate to Brewer, despite the higher costs involved in the
process.
“It’s
obviously cheaper and more convenient (for Red Shield) to bring their
leachate here,” Stetson said. “But even if we do end up taking it, there
are still some questions about where we’ll put it, whether it should be
here or on a remote site. We’ll also need some tankage. It takes 65-80
minutes for the trucks to dump the leachate. We can handle 10-100
gallons a minute. (As) another part of the agreement, they’re not
allowed to haul in anything when it’s raining or the pilot study will be
shut down.”
Once
the eight-week study is completed, Wright, Pierce will evaluate the
results and report back on their findings. From that point, the process
would shift into the hands of the Old Town city council, who would vote
on whether to allow Red Shield to enter into a permanent arrangement
with the wastewater treatment plant. |