
Boiler
March 21, 2007
Further testing is need to determine when Red Shield will be allowed to
burn construction and demolition debris (C and D) in its biomass boiler,
according to Ed Logue of the Maine Department of Environmental
Protection.
On Monday,
Logue said that an “air compliance person” was on site to check on the
progress of repairs to the boiler following two incidents in which soot
fell on the property of some Bradley residents. The boiler was shut down
last week so that the source of the problem could be located and repairs
could be made. After work was done on the soot collection system, the
boiler was restarted on Friday.
“It was
allowed to run over the weekend on whole tree chips,” Logue said. “There
can absolutely no burning of C and D wood until we’re sure that
everything is working at 100 percent.”
Following the
soot emissions incident in Bradley two weeks ago, the DEP sent a letter
to Red Shield, ordering them to stop burning its usual 50/50 mix C and D
wood and green chips. According to Logue, a lawyer for Red Shield
informed the DEP that the company had already complied with the
directive and was burning only green wood chips in the boiler.
Logue said
that the attitude of Red Shield officials on Monday was “optimistic”
regarding the immediate future of the biomass boiler, but that there
were other issues to be resolved apart from the recent “malfunction” of
the boiler. Some ash samples taken from the boiler site have tested at
toxic levels since February, and the DEP is conducting more tests to
determine the reason for those high readings. In accordance with DEP
guidelines, anything over five milligrams per liter is considered toxic
and can’t be buried in the state of Maine. Some ash that was produced at
the same time as the ash now being tested has been deposited in the
Juniper Ridge Landfill in West Old Town, but Casella spokesman Don
Meagher said last week that the section of the state-owned landfill
containing the ash has been isolated and is no longer active. If the ash
deposited there is found to be toxic, he said that it would be removed
through a process determined by Casella, Red Shield, and the DEP.
“We hope to
know more by mid-week,” Logue said. “At that point, maybe we can bring
some resolution to the questions regarding the ash and what’s going on
at the site.”
|