
Landfill construction like a “piece of cake”
October 5, 2006
By Greta Sproul
Officials
at the Juniper Ridge Landfill announced last month that they are in the
process of expanding the site off Route 16 in Alton. In order to make
space for additional deposits to the landfill, Casella Waste Systems,
Inc has begun construction on a 6-acre section of land designated as
“cell 3-B.” The construction process is beginning just as the available
space in the 4-acre section of the landfill known as “cell 3-A” is
nearing its capacity to hold more waste deposits. Construction of the
new cell won’t be completed and operational until the first of next
year, but Casella spokesman Don Meagher says that cell 3-A still has
enough space to hold additional deposits of waste until then.
“There’s
been an increase in the amount of waste we’ve been getting,” Meagher
said. “That has a lot to do with certain clean-up situations going on at
the Naval Air Station in Brunswick and a tannery in South Paris. We’re
also taking a lot of waste that would otherwise be going to the Pine
Tree Landfill in Hampden.”
Meagher
adds that, despite the increased tonnage in waste material over the
summer, there hasn’t been any real increase in the number of odor or
other complaints noted in the company’s record log. A total of 12 odor
complaints were recorded for the month of August, but most of those were
primarily related to the excavation process that preceded construction
of cell 3-A, says Meagher. He adds that his company encourages such
complaints from the people who own land abutting or in the footprint of
the landfill.
“When we
get a call on the odor hotline, it alerts us to the possibility that
something could be wrong,” he said. “We investigate immediately to see
if the flows are down or a trench could be open.”
But even
as Casella works to expand Juniper Ridge, Meagher says that he is very
much aware of the concerns some local residents still have about the
nature of the waste that is dumped into the landfill, as well as the
process the company uses to verify the contents of that waste material.
“The
process is the same one that we use in Hampden,” he said. “Each
(landfill) customer checks is given an approval number that they show to
the scale-master during the weigh-in process. That approval number lets
the scale-master know whether a specific load of waste needs to be
analyzed or tested, and how much of it the customer is bringing into the
landfill.”
Meagher
says that he understands the concerns some people have that unapproved
waste might find its way covertly into the landfill, but that there are
ways to verify whether or not unapproved materials have been dumped at
the site.
“Basically, we work on the honor system because most people are honest
about what they bring into the landfill,” he said. “But if someone did
dump unapproved waste into the landfill, it would eventually dissolve
and the chemicals would work their way into the leachete, which is
sampled on a quarterly basis.”
Another
concern that many people have is about the construction of the landfill
itself, Meagher says.
“Some
people have the idea that we just put waste into a big hole in the
ground and cover it over with dirt,” he said. “It’s much more
environmentally than that. This may not be the best analogy, considering
the subject, but the way the landfill is constructed is similar to the
layers in a piece of cake.”
Meagher
explains that the base liner system used in the landfill begins with a
six ounce layer of nonwoven geotextile, over which there is a 12 inch
layer of underdrain sand and a 24 inch layer of compacted clay. Above
those initial three layers, there are four more layers that consist of
geosynthetic clay liner, 80 milligrams of HDPE textured geomembrane, and
drainage geocomposite. The two top layers of the “landfill cake” are
made up of 12 inches of leachete collection sand and another 12 inches
of frost protection material known as NITC.
Juniper
Ridge Landfill is the first and only state-owned landfill in Maine. It
was purchased from Georgia-Pacific in 2004 and began operating last May.
It currently employs about 20 people, including four scale-masters, one
of whom doubles as a night security person. At present, the landfill is
open seven days a week, but that schedule is contingent on changes in
the amount of deposits to the site, Meagher says.
|