
East channel of Penobscot closed for bridge
demolition
September
21, 2006
The
east channel of the Penobscot River between Old Town and Milford was
closed to boat traffic last Friday. According to a press release from
Devin Anderson, Project Manager for MaineDOT, boat traffic under the
Route 2 Bridge is currently prohibited due to concerns that debris may
fall while the bridge is being demolished. The demolition will not
affect traffic on the detour bridge, the portion of the new bridge that
has been constructed so far, or the adjacent railroad trestle.
Demolition of the existing bridge, which consists of a series of
concrete arch spans, is already underway. But, Anderson says, due to the
poor condition of the existing bridge, the contractor hired by the
Department of Transportation, Reed & Reed of Woolwich, Maine, had
encountered unanticipated difficulty in removing the concrete arches in
manageably small pieces.
The
original demolition plan called for catching the concrete debris on
temporary false work placed under the arch spans. But the contractors
found this approach to be impractical after large portions of the
concrete arches were knocked loose during the demolition process. The
revised demolition plan will allow the concrete to fall to the river
bottom, then the debris will be removed using a crane equipped with a
clam-bucket shell.
“The
inherent design of this structure does not lend itself to removing the
arch spans in small pieces,” Anderson explained. “This revised
demolition plan will provide a safer work environment for the
contractor’s people, but could present a hazard to boaters. State and
federal environmental agencies have been notified of this and concur
that the change is necessary for the safety of the workers. Signs
alerting boaters of the closure have been posted.”
Stage
One of the bridge replacement project has been completed, with sewer
lines and Verizon telephone lines switched and installed to portions of
the new bridge. Demolition of the existing bridge will continue through
November, as portions of the new bridge are built concurrently. The
current work on the bridge is part of a $9 million bridge replacement
project which is scheduled to be completed in 2008. The MaineDOT first
began working on the bridge last July.
|